Batterilager

Domsjö

Örnsköldsvik, Västernorrland (SE2)
Capacity
6 MW
Battery storage
Storage capacity
12 MWh
Stage
Permitting
Operative
2027

About

In Domsjö, Örnsköldsvik, a battery storage facility with a capacity of 6–10 MW is planned.

We have signed a lease agreement for the land and started planning. Talks are ongoing with the electricity grid owner about the grid connection.

A battery storage facility could strengthen security of supply and balance the local electricity grid when the need arises. It is a quick and flexible way to temporarily contribute more electricity at times when the load is at its highest and store electricity when consumption is low.

More projects

Under development

Just north of Heby locality, we are carrying out early project development to establish a battery storage facility with a capacity of 50–80 MW. There is major power distribution grid development ongoing in the region.

Under development

A land lease agreement has been secured for the development of a battery energy storage system (BESS) in Brunna, Upplands-Bro municipality. The site is considered well suited for battery storage deployment in light of the ongoing grid developments in the area.

Under development

In Domsjö, Örnsköldsvik, a battery storage facility with a capacity of 6–10 MW is planned.